Construction Project Updates
In collaboration with the SUNY Construction Fund and the Dormitory Authority of the State of New York, SUNY Plattsburgh’s facilities department oversees many constructions projects each years to meet the evolving needs of our campus community.
Champlain Valley Hall
Slate Roof Replacement
Learn More About This Project — Updated Feb. 14, 2022
- Details
Update — Slate is about 100% completed. All that remains is a minor amount of chimney repair, site work, and closeout documentation.
Timeline — Expected to be complete by end of Spring 2022.
Scope — The existing sloped slate roof of CV Hall is at the end of its functional life expectancy. The slate along with all underlayments, copper roofing, fascia and trim will be replaced with new products.
- Photo Gallery
Photos sorted by date taken.
deFredenburg Hall
Bathroom Renovation
Learn More About This Project — Updated Jul. 21
- Details
Update — The design includes the full replacement of the bathroom mechanical systems, reconfiguration of the space, new finishes, ADA accessibility, increased privacy and reconfiguration of the CD apartment kitchen area. Bid documents were completed and due to the pandemic the project will be shelved and considered in the future.
Timeline — Project is on hold.
Scope — The design includes the full replacement of the mechanical systems as well as the reconfiguration of the bathroom space. The bathrooms will feature ADA accessibility as well as increased privacy for the residents.
- Photo Gallery
Photos sorted by date taken.
Feinberg Library
Masonry Restoration
Learn More About This Project — Updated Feb. 14, 2022
- Details
Update — Work is scheduled to begin March 2022 and extend through the summer.
Scope — This project is intended to repair and preserve the masonry facades of Feinberg Library. This restoration effort will include the replacement of deteriorating brick and other cast concrete components, installation of new flashing and control joints, repointing existing brick and the application of a masonry sealant.
- Photo Gallery
Photos sorted by date taken.
Field House
Gym Floor & Bleacher Replacement
Learn More About This Project — Updated Feb. 14, 2022
- Details
Update — Bleachers are 100% removed, as well as the mercury sports floor abated. The new jumping pit is 50% complete. Painting is in progress as well as cleaning of the upper roof steel and ductwork. New filters for the AHU’s are being installed. The new bleachers are scheduled to be completed on May 13, 2022.
Estimated Timeline — Project completion is expected in June of 2022.
Scope — The existing track surface will be removed and reinstalled with a new and upgraded running surface, as well as the inner rubberized flooring of the gym replaced with an artificial grass turf playing surface. The existing bleachers will be replaced, and new jumping pits for track relocated outbound of the track running surface. New lighting and overall painting is included.
- Gallery
Photos sorted by date taken.
Hawkins Hall
Nursing Lab Renovation
Learn More About This Project — Updated Feb. 14, 2022
- Details
Update — Finished flooring is installed, painting is approximately 90% complete. Cabinetry is in progress. IVS (camera system) will be onsite to install the cameras February 2022
Estimated Timeline — Spring 2022
Scope — The existing nursing labs 205 and 255 of Hawkins will be completely renovated to include numerous individual simulation labs, that will have updated finishes and features to improve learning opportunities.
- Photo Gallery
Photos sorted by date taken.
Hood Hall
Bathroom Renovation
Learn More About This Project — Updated Feb. 14, 2022
- Details
Update — Abatement has been completed on floors 2 through 9 and the ground floor. Abatement continues on the first floor. Floors 9 through 5, electrical, plumbing, HVAC, and fire suppression rough in are in process. In addition on floors 9 through 5 the GC is framing partitions, shaft walls, sheetrock installation, self leveling underlayment, and fire stopping, Floors 4 through 2 general demolition is taking place.
Timeline — Substantial completion is anticipated for late April 2022.
Scope — The design includes the full replacement of the mechanical systems as well as the reconfiguration of the bathroom space. The bathrooms will feature ADA accessibility as well as increased privacy for the residents.
- Photo Gallery
Photos sorted by date taken.
Kehoe Administration Building
Masonry Restoration
Learn More About This Project — Updated Feb. 14, 2022
- Details
Update — Work on the masonry restoration at Kehoe is on hold for the winter. The large scaffolding, called mast climbers, are still in place so the contractor can jump back in as soon as weather permits. Work is expected to restart in mid-March on the west side of the building. There will be some impacts to parking areas around the building during construction.
Estimated Timeline — Work began July 2021 and will continue until cold weather arrives then resume Spring 2022 as warmer weather permits.
Scope — This project will address sections of failing masonry causing water infiltration and the repair of exposed rebar. The project includes a sprayed concrete finish “shotcrete” on the exposed concrete faces of the building, as well as limited brick repointing (grinding out of deteriorated mortar, and replacement of new mortar).
- Photo Gallery
Photos sorted by date taken.
Parking Lot Replacement
Learn More About This Project — Updated Feb. 14, 2022
- Details
Update — Electric Vehicle stations have been installed, following up on their inclusion on our campus account with ChargePoint.
Estimated Timeline — Completed by Summer 2022
Scope — The existing pavement surface will be removed, and a new stone subbase and new asphalt layers replaced. Installation of 4 electrical vehicle charging stations. Existing manholes and drainage structures to be repaired and/or replaced as needed.
- Gallery
Photos sorted by date taken.
Roof Replacement
Learn More About This Project — Updated Feb. 14, 2022
- Details
Estimated Timeline — Work is tentatively scheduled for the Spring/Summer 2022.
Scope — Project has been awarded to Titan Roofing. We are awaiting a construction schedule, and Notice to Proceed. A coordination meeting with the masonry project is forthcoming to determine the feasible start date of the roof replacement.
- Gallery
Photos sorted by date taken.
Memorial Hall
Phase I Renovation
Learn More About This Project — Updated Feb. 14, 2022
- Details
Update — The first phase of the Memorial Hall Renovation is substantially complete and open for use! This phase of the project includes a fully renovated lobby, a new recreation gym and renovated restrooms. Remaining scope for this phase includes an audio visual package and furniture for the lobby.
Scope — Memorial Hall is dedicated to the college’s athletic and student recreational services. The building has been operational since 1963. This project will renovate the building to improve increased efficiencies and utilization as well as address the changing functional needs. Building mechanical systems are included for renovation in the project scope. Phase I of the renovation is expected to start late during the winter of 2019/2020. This Phase will incorporate the replacement of the existing pool with a new recreation gym, a revitalized main third floor lobby, new restrooms on the third floor, and new surge space on the first floor to facilitate moving of program space for future phases.
- Photo Gallery
Photos sorted by date taken.
Phase II Renovation
Learn More About This Project — Added Feb. 14, 2022
- Details
Update — Project has been bid, waiting for Notice of Award to MLB Construction. We have moved out the remaining fitness equipment from the Phase II work area, but need to formulate a list of further items to be removed by the campus prior to construction starting.
Timeline — The project is currently in contracting and construction work is expected to begin in early summer.
Scope — This Phase will incorporate the replacement of mechanical systems for the competition gym, new bleachers and new floor. It will also completely renovate the second floor coaching offices, sports medicine and team locker rooms. The first floor will be a major renovation of the fitness center space, including a much needed expansion of the fitness center space. The climbing wall will be relocated and be replaced with new features as well. The existing exterior masonry will be repointed, marble headers and jambs replaced, as well as flashing repaired or replaced.
- Photo Gallery
Photos Coming Soon
Myers Fine Arts
Ventilation Upgrades
Learn More About This Project — Updated Feb. 14, 2022
- Details
Update — Project was bid Feb. 2022. The apparent low bidder is L.H. LaPlante Mechanical.
Estimated Timeline — Work is tentatively planned to start the summer of 2022, and complete in time for the Fall Semester of 2023.
Scope — Initial scope will be to replace in kind the current air handling units with new upgraded energy efficient units, along with a new duct distribution system. Functional improvements to include possibly a dust collection and upgraded exhaust system in the scene shop of the theatre. The areas to be addressed include Hartman Theatre, offices on the east end of the building, scene shop, black box theatre, and ancillary support spaces.
- Photo Gallery
Photos coming soon.
Masonry Restoration
Learn More About This Project — Updated Feb. 14, 2022
- Details
Update — Design is anticipated to begin in the spring of 2022
Scope — This project will address sections of failing masonry causing water infiltration and the repair of exposed rebar. The project includes a sprayed concrete finish “shotcrete” on the exposed concrete faces of the building, as well as limited brick repointing (grinding out of deteriorated mortar, and replacement of new mortar).
- Photo Gallery
Photos coming soon.
Yokum
Masonry Restoration
Learn More About This Project — Updated Nov. 17
- Details
Update — Design is anticipated to begin in the spring of 2022
Estimated Timeline — Construction is delayed currently due to COVID-19 related budget restrictions.
Scope — This project will address sections of failing masonry causing water infiltration and the repair of exposed rebar. The project includes a sprayed concrete finish “shotcrete” on the exposed concrete faces of the building, as well as limited brick repointing (grinding out of deteriorated mortar, and replacement of new mortar).
- Photo Gallery
Photos coming soon.
Completed Projects — Updated Jul. 21
- Angell College Center Bathroom Upgrades
Construction completed Fall 2019. This project included a complete replacement of all finishes within the six existing public bathrooms. The existing bathrooms by the 1st floor main entrance had two additional unisex bathrooms constructed in front of them by borrowing space from the existing bathrooms. All bathrooms were retrofitted to comply with the current accessibility standard in the NYS Building Code.
- Angell College Center Center for Diversity, Equity, and Inclusion (formerly Multicultural
Center)
Construction has been completed and the center was opened prior to the start Spring 2019. AEDA was selected as the design firm for the multicultural unity space. The project kicked off in summer 2018 with a construction completion date of Jan. 7, 2019. Student focus groups were engaged during the spring 2018 semester regarding the program needs for a multicultural unity space. It will include Title IX offices.
- Central Campus Podium Phase I & II
This extensive rehabilitation of the existing elevated walkway, called the podium, which connects numerous buildings at the second-floor level. It involved removing the existing walking surface pavers down to the existing structural slab. A new membrane, drainage and stamped concrete walking surface was installed. An impressed current cathodic protection system was installed to protect the reinforcing steel in the structure. Also new to the structure, a radiant heat snow melt system in the hardscape portions, to minimize if not negate snow removal operations. The reduction in heavy snow removal equipment and use of chlorides as deicers will serve to vastly extend the life of the Podium. New green spaces spruce up the walkways along the railing edges, and the underside was rehabilitated to fix all the damaged concrete from water infiltration. The two approaches to the bridge over Broad St. were also completely replaced.
Phase I included the podium spanning from the walkway starting at Parking Lot 8 of Yokum Hall by Beaumont Hall and completing at Hudson Hall. Construction began Aug. 2016 and ended Dec. 2018.
Phase II included the podium spanning from Parking Lot 28 at the walkway between ACC and Feinberg Library, over to Myers, Yokum and Kehoe. Construction began Aug. 2016 and ended Jan. 2019.
- Central Heating Plant — High Temperature Hot Water Generator Upgrade & Renovation
(Phase I & II)
The work under Phase I involves a replacement of one HTHW Generator, reconfiguration of piping, abatement of asbestos containing insulation, replacement of pumps and valves, as well as a reconfiguration of the control room and bathrooms. The work under Phase II involves a replacement of two HTHW Generators and associated piping. This will complete the renovation work of the Central Heating Plant.
- Clinton Dining Hall
This project involved a complete revamping of the dining hall and kitchen equipment. It will provide a significant improvement in the campus dining experience with presentation of the cooking experience, new venues, dining level bathrooms, new furniture, new décor and finishes. Mechanical, electrical and plumbing upgrades will be provided as well to serve the new kitchen equipment and users in the dining hall. The project will be phased throughout the summers and academic sessions to maintain a completely operable and accessible dining hall throughout the renovation.
- Harrington Hall Bathroom Renovation
Construction of phase two was completed on 12/15/20. The design includes the full replacement of the mechanical systems as well as the reconfiguration of the bathrooms into individual private bathrooms. The bathrooms will feature ADA accessibility as well as increased privacy for the residents.
- Hawkins Hall Chiller Project
This project was completed Spring 2019. Trane units were set and the installation of the glycol piping to the new units occurred. Final testing was completed prior to the end of the spring semester.
- High Temperature Hot Water Piping Replacement
This project wrapped up within the first few weeks of Fall 2018. Fuller Excavating performed very well getting the HTHW back up and running for the start of the fall semester. This project included a replacement of the HTHW lines for Zones 1 and 2 from the vault within the Central Heating Plant to the manholes across the street along Sanborn Ave. Extension. Traffic will be restricted in the immediate area of construction. Access to the Service Building, CHP, and the Maintenance Garage will be maintained via Rugar St.
- Hudson Hall Parking Lot Restoration
The project was completed Fall 2019. The existing pervious concrete parking lots deteriorated to the point of severe degradation. The project removed the concrete and loose stone subbase. There is new compacted subbase stone course, new asphalt base and top courses, some new curbing and line striping. Hudson Main and annex parking lots were stripped down to subgrade level and asphalt layers installed. Curbing and sidewalks received limited replacement to address any damaged areas, as well as any storm water redirecting to improve drainage and safety concerns.
- Kent Hall Renovation
Construction started on 5/17/19 and was completed on 7/21/20. The design is focused at providing new building finishes, building envelope improvements, full service kitchenettes/lounges of floors 1 through 3, inclusion of food service vendor, reconfiguration of building living space to suites with private bathrooms including ADA bathrooms, full coverage sprinkler system, electrical system upgrades, mechanical system upgrades including full building AC, generator power for life safety systems, elevator, site improvements that will remove the concrete hardscape that now exists.
- Macomb Hall Renovations
Construction began May 2017 and was complete Spring 2020. It provided new building finishes, building envelope improvements, laundry areas on floors 1 through 3, full service kitchenettes of floors 1 through 3, full coverage sprinkler system, generator power for life safety systems, building envelope enhancements, new elevator, site improvements that will remove the concrete hardscape that now exists, and total renovation of the existing bathrooms that will include ADA accessibility as well as increased privacy. Finally, this renovation will include the reconfiguration of the ground floor spaces into office spaces that will house EOP and SSS.
- Mason Hall Renovations
Construction began May 2017 and was complete Spring 2020. The project provided the full replacement of the mechanical systems as well as the reconfiguration of the bathrooms into individual private bathrooms. The bathrooms will feature ADA accessibility as well as increased privacy for the residents.
- Myers Fine Arts Replacement of Winkle Court Skylight Glazing
Design and construction completed Fall 2019. This project included a replacement of the glazing of the existing skylight, with a new energy efficient, tinted glazing. The existing glazing is structurally sound, however is not insulated and not UV resistant. The seals have all deteriorated and the skylight is leaking in many locations. The new glazing will improve the UV resistance as it will be tinted and reflect much of the heat in the summer. It will also be weather tight.
- Sibley Hall New Offices for the Center for Neurobehavioral Health & Psychology Department
The Psychology Department and Clinics have moved into the new spaces in July 2017. A complete renovation of the South end of Sibley Hall, including a new second floor in the gymnasium space. The gym has been taken off line and replaced with offices and clinic space for the psychology dept. Other department moves will be occurring within the current Third Age, NCTRC, and EHS locations to support this renovation.
- Whiteface Hall Renovation
The design involved the reconfiguration of the existing floors into one large suite that will provide more open movement and easier access to social spaces, complete renovation of the bathrooms that will provide increased privacy, full service kitchenette’s on floors 2 through 9, study lounge on floors 2 through 9, additional study lounges on the 2nd floor, addition of a larger lounge on the 9th floor facing south that will allow residents to take in the views of the lake that this building has to offer, reconfiguration of the lounge areas on the first floor that will interconnect with a communicating staircase to the lounge in the basement, reconfiguration of the lobby and RD Office area to provide much needed work areas for staff, renovation of the res life offices, renovation of the RD apartment that will provide more living area, site improvements that will provide welcoming gathering places, upgrade of all building services, full coverage sprinkler system, installation of energy efficient windows and installation of exterior insulation panels that will mirror deFredenburgh, Moffitt and Hood Hall.
- Wilson Hall Renovation
Construction was completed on July 17, 2017 and students have moved in!
Renovation of the 9 story resident hall began on May 24, 2016 with a completion date of July 17, 2017. The work involved the reconfiguration of the existing floors into one large suite that will provide more open movement and social spaces, complete renovation of the bathrooms that will provide increased privacy, full service kitchenette’s on floors 2 through 9, study lounge on floors 2 through 9, rebuilding of the elevators, reconfiguration of the lounge areas on the first floor that will interconnect with a communicating staircase to the lounge in the basement, reconfiguration of the lobby and RD Office area, relocation of the RD apartment that will provide more living area, site improvements that will provide welcoming gathering places, upgrade of all building services, full coverage sprinkler system, installation of energy efficient windows and installation of exterior insulation panels that will mirror deFredenburgh, Moffitt and Hood Hall.
Minor Critical Maintenance Projects
- Projects in PlanningNone
- Projects in Progress
Angell College Center
Signage expected completion May 2020
Campus Signage
12" Exterior building identifiers
Field House
Storage Building — Contractor is finalizing subcontractors, has been working on submittals and a baseline progress schedule. Tentatively, has the modular building components arriving the first week of April 2022
Hawkins Hall
Courtyard John Ettling & Lisa Lewis Courtyard, currently out to bid, planned construction summer of 2020.
Parking Lot Signage
Logo replacement is on-going
Sibley Hall
100 Section — Construction of six storage closets, ceiling, lighting, and flooring upgrades
Courtyard — Make-A-Wish courtyard renovation construction scheduled Spring 2020
Throughout Building — Light and ceiling replacement
Tower Way
Exterior lighting — Scheduled Fall 2019
- Completed
102 Broad Street
Exterior painting
Angell College Center
Rear courtyard retaining wall repair
Help Desk Renovation
Cardinal lounge/Alumni Conference room carpet
Cardinal lounge/Alumni Conference room lighting — New LED fixtures installed
Center for Student Involvement
Student Affairs Suite
Beaumont Hall
Second Floor Upgrade
Robotics and third floor classroom
Campus Fire Alarm
Upgrades — All academic and residential buildings complete
Campus Parking Lot Signage
Campus Sidewalk
Various sidewalk replacements
Feinberg
Walkway Leading to Podium by Feinberg Loading Dock Before
Hawkins Hall
Flooring Upgrades
Kehoe
Parking lighting upgrade
Administration and Finance suite
MacDonough Hall
Tennis court resealed
Myers Fine Arts
Rainbow Crosswalk
Sibley Hall
Suite 400 — Ceiling, lighting, and flooring upgrades, completed
Student Health and Counseling Center
Check-In Sheds
Questions?
Contact the following individuals to learn more about a specific project.
- Tyson Moulton, Assistant Vice President Facilities and Operations oversees minor critical maintenance projects.
- Rick Larche, Capital Project Manager oversees all capital projects except residence hall projects
- Jules LaPoint, Central Plant Coordinator oversees residence hall construction projects.